Anesthesia machine installation process-1

Anesthesia machine installation process 1. Open the package 2. Anesthesia machine instalation (1)、Install wheels and poles Schematic diagram (2)Install the anesthesia machine and tighten the 4 screws. (3) Install evaporation tank a)、put the evaporator on the hanger. Lock switch Lock switch The "lock switch" is in this position and the installation is complete. b)、Rotate the "lock switch" 90° clockwise。 Schematic diagr

 Open the catalog to page 1
Anesthesia machine installation process-2

2、Pipeline connection steps (1)Anesthesia machine line connection: Exhaust gas discharge line Breathing circuit

 Open the catalog to page 2
Anesthesia machine installation process-3

4 、Soda lime replacement Turn the screw to replace the soda lime Note: The slot of the soda lime bucket must be aligned, otherwise it will be easy to leak

 Open the catalog to page 3

All Bmv-vet catalogs and technical brochures

  1. BMO-210A Vet

    4  Pages

  2. MX5 Go

    4  Pages

*Prices are pre-tax. They exclude delivery charges and customs duties and do not include additional charges for installation or activation options. Prices are indicative only and may vary by country, with changes to the cost of raw materials and exchange rates.