Repowering Pipe
8Pages

{{requestButtons}}

Catalog excerpts

Repowering Pipe - 1

Repowering Pipe system Mixer replacement without tank emptying

Open the catalog to page 1
Repowering Pipe - 3

Repowering mixers ... an opportunity to increase efficiency Repowering mixers In Germany there are currently around 7,000 biogas plants in operation with approx. 30,000 mixers working in their digesters. The estimated average power consumption per operating hour and mixer is approx. 10 kW/h. With an annual operational time of 25 % this gives an incredible power consumption of 657,000 MWh. Assuming an electricity price of EUR 0.155 per kWh, the cost is approx. EUR 100 million/year. If it is possible over the next few years to convert existing biogas plants to highly efficient mixer...

Open the catalog to page 3
Repowering Pipe - 4

„Repowering Pipe“ system Mixer replacement without tank emptying Repowering Pipe“ principle The greatest obstacle in the path of efficient mixer technology up to now has been the need to empty digesters for installation. As an operator you are aware of the consequences of having to bring the process back to a stable level after refilling. „Downtime costs amounting to thousands of Euros have up to now been the re

Open the catalog to page 4
Repowering Pipe - 5

With the new and unique „Repowering Pipe“ system, we can install mixers in a few hours without emptying tanks and therefore reduce downtime costs to a minimum. Thanks to the „Repowering Pipe“ principle in combination with highly efficient mixers, we are providing our customers with the opportunity to rapidly recoup their investment in efficient mixer technolo

Open the catalog to page 5
Repowering Pipe - 6

Examples of efficiency increases from future-oriented digester mixers Biogas plant location: Tuningen / Germany Output: 1.050 kW Substrate: Grass, maize, hole crop silage Digester (ring digester): External diameter: 32 m Internal diameter: 24 m Height: 6m Net volume: 1.900 m³ Installation without digester emptying with the „Repowering-Pipe“ system Mixer technology - initial situation Type Quantity Rated output Consumption / operating hour Runtime in kW kWh % Long-shaft mixer Submersible mixer Mixer technology - after retrofitting Type Quantity Rated output Consumption / operating hour...

Open the catalog to page 6
Repowering Pipe - 7

Biogas plant location: Deinsteed / Germany Output: 1.200 kW Substrate: Maize, poultry manure Digester: Diameter: 22 m Height: 6 m Net volume: 2.000 m³ Installation without digester emptying with the „Repowering-Pipe“ system Mixer technology - initial situation Type Quantity Rated output Consumption / operating hour Runtime in kW kWh % Submersible mixer 394.200 Mixer technology - after retrofitting Type Quantity Rated output Consumption / operating hour Runtime in kW kWh % Submersible mixer

Open the catalog to page 7
Repowering Pipe - 8

Scan me and find out more about Maier Energie & Umwelt Certified by TÜV Süd Approved specialist company under the German Water Economy Act (WHG) We are a member of the German Biogas Association (Fachverband Biogas e.V